ARU and Interconnection piping - 10+ Programme

Within the 10+ Programme  we performed the following works for the LOTOS Group:

  1. Amine Regeneration Unit & Sour Water Stripping System, including:
    – Fabrication and assembly of piping in diameters ½”-30”, ca. 350 t,
    – Steel structures erection – ca. 500 t,
    – Equipment erection – ca. 900 t.
  2. Mechanical works – fabrication and erection of piping (1200 t) in diameters  ½” -24″ together with commissioning and start up of the proces plant within the I, II, III stage of the Interconnection Unit construction in Gdańsk refinery.