LNG Terminal - piping erection

For Polskie LNG Project we have executed piping and related works as follows:
– piping erection on Corridor Area – 310 t of SS (DN200, DN700, DN1050),
– piping erection on Utility and SCV (Submerged Combustion Vaporizers) Area – 112 t 42 % of SS and 58% of CS (DN15 – DN300),
– piping erection of Send Out Line– 200 t of L555MB steel (DN800 x 17,5 mm) – under GAZ System requirements.

Total: 622 t of piping and 150 t of supports.