LNG Terminal - tanks

2011-2013: for Polskie LNG Project we have executed construction works of the two LNG tanks of capacity 160.000m3 each, consisting of the site assembly and erection of compression rings and site assembly of roof segments of the overall tonnage about 1000 t (roof surface of 4717m2).